Case Studies

Support Services

Renewables - Prime Four Kingswell Business Park

  • Client:
    Drum Kingswell Business Park Ltd
  • Value:
    £500k
  • Completion :
    February 2014
  • Managing Contractor:
    Sir Robert McAlpine

Prime Four was designed to provide world class HQ facilities for international occupiers including Nexen, Apache and Transocean. The first phase of the Prime Four business park, near Kingswells, comprised of three high-spec office buildings and a global training centre for companies working in the offshore oil and gas industry for Nexen spread over four plots.

FES Renewables were appointed to carry out the supply, installation and commissioning of 4no CHP plants including processing G59 applications. The installation was carried out in phases to allow the continued use of the building throughout the project. The four individual commercial buildings now have their own combined heat and power plant (CHP) ranging from 25kW to 100kW in size.